Original Cost
₹320 Cr
Baseline estimate
Revised Cost
₹348 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+8.7%
+₹28 Cr increase
Remaining
₹348 Cr
Budget left
Spent
₹0 Cr
Remaining
₹348 Cr
Total
₹348 Cr
Original Cost
₹320 Cr
Revised Cost
₹348 Cr
Increase
+₹28 Cr
Escalation
+8.7%
Project Approved
Construction / Implementation
Original End Date
04/04/2022
Revised Completion
30/06/2026
Completed
Cost has increased by ₹28 Cr (8.7%) from the original estimate of ₹320 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹348 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.