Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpass VUP, 1 nos. of Light Vehicular Underpass LVUP, 1 nos. of Pedestrian Underpass PUP, 1 nos. of Foot Over Bridge FOB and A2 side approach of Jharpokharia Flyover at Km.215.270 in Baharagora-Singhara section of NH-49
Original Cost
₹321 Cr
Baseline estimate
Revised Cost
₹245 Cr
Latest approved cost
Expenditure
₹55 Cr
Spent to date
Utilization
22.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹190 Cr
Budget left
Budget Utilization
22.6%Spent
₹55 Cr
Remaining
₹190 Cr
Total
₹245 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
02/05/2026
Revised Completion
31/10/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹321 Cr — no cost escalation recorded.
Expenditure stands at ₹55 Cr, which is 22.6% of the revised project cost.
Remaining budget: ₹190 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpass VUP, 1 nos. of Light Vehicular Underpass LVUP, 1 nos. of Pedestrian Underpass PUP, 1 nos. of Foot Over Bridge FOB and A2 side approach of Jharpokharia Flyover at Km.215.270 in Baharagora-Singhara section of NH-49 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹321.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpas"?
- Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpass VUP, 1 nos. of Light Vehicular Underpass LVUP, 1 nos. of Pedestrian Underpass PUP, 1 nos. of Foot Over Bridge FOB and A2 side approach of Jharpokharia Flyover at Km.215.270 in Baharagora-Singhara section of NH-49 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹321 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹321 Cr and has been revised to ₹245 Cr — a cost overrun of -23.7%. Expenditure to date: ₹55 Cr (22.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618592. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.