Original Cost
₹321 Cr
Baseline estimate
Revised Cost
₹245 Cr
Latest approved cost
Expenditure
₹49 Cr
Spent to date
Utilization
19.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹196 Cr
Budget left
Spent
₹49 Cr
Remaining
₹196 Cr
Total
₹245 Cr
Project Approved
Construction / Implementation
Original End Date
02/05/2026
Revised Completion
31/10/2027
Completed
Project is within original budget of ₹321 Cr — no cost escalation recorded.
Expenditure stands at ₹49 Cr, which is 19.8% of the revised project cost.
Remaining budget: ₹196 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.