Roads & HighwaysIPM · Central Project#618592

Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpass VUP, 1 nos. of Light Vehicular Underpass LVUP, 1 nos. of Pedestrian Underpass PUP, 1 nos. of Foot Over Bridge FOB and A2 side approach of Jharpokharia Flyover at Km.215.270 in Baharagora-Singhara section of NH-49

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹245 CrUtilization: 22.6%

Original Cost

₹321 Cr

Baseline estimate

On budget

Revised Cost

₹245 Cr

Latest approved cost

Expenditure

₹55 Cr

Spent to date

Utilization

22.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹190 Cr

Budget left

Budget Utilization

22.6%
0%25%50%75%100%

Spent

₹55 Cr

Remaining

₹190 Cr

Total

₹245 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/05/2026

Revised Completion

31/10/2027

Completed

Project Details

Project Code618592
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹321 Cr
Revised Cost₹245 Cr
Expenditure₹55 Cr
Original End Date02/05/2026
Revised Date31/10/2027

Project Intelligence

Project is within original budget of ₹321 Cr — no cost escalation recorded.

Expenditure stands at ₹55 Cr, which is 22.6% of the revised project cost.

Remaining budget: ₹190 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpass VUP, 1 nos. of Light Vehicular Underpass LVUP, 1 nos. of Pedestrian Underpass PUP, 1 nos. of Foot Over Bridge FOB and A2 side approach of Jharpokharia Flyover at Km.215.270 in Baharagora-Singhara section of NH-49 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹321.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpas"?
Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. of Vehicular Underpass VUP, 1 nos. of Light Vehicular Underpass LVUP, 1 nos. of Pedestrian Underpass PUP, 1 nos. of Foot Over Bridge FOB and A2 side approach of Jharpokharia Flyover at Km.215.270 in Baharagora-Singhara section of NH-49 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹321 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹321 Cr and has been revised to ₹245 Cr — a cost overrun of -23.7%. Expenditure to date: ₹55 Cr (22.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618592. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of 8 nos. of Elephant Underpasses EUPs, 1 no. o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.