Balance work of 2L PS from Km 30.800 to Km 70.800 and 2L with Rigid Carriageway from Km 70.800 to km 84.120 of Khanapur- KA/GOA Border section of NH-4A
Original Cost
₹227 Cr
Baseline estimate
Revised Cost
₹149 Cr
Latest approved cost
Expenditure
₹110 Cr
Spent to date
Utilization
73.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹39 Cr
Budget left
Budget Utilization
73.8%Spent
₹110 Cr
Remaining
₹39 Cr
Total
₹149 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
21/05/2024
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹227 Cr — no cost escalation recorded.
Expenditure stands at ₹110 Cr, which is 73.8% of the revised project cost.
Remaining budget: ₹39 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Balance work of 2L PS from Km 30.800 to Km 70.800 and 2L with Rigid Carriageway from Km 70.800 to km 84.120 of Khanapur- KA/GOA Border section of NH-4A is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹227.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Balance work of 2L PS from Km 30.800 to Km 70.800 and 2L with Rigid Carriageway"?
- Balance work of 2L PS from Km 30.800 to Km 70.800 and 2L with Rigid Carriageway from Km 70.800 to km 84.120 of Khanapur- KA/GOA Border section of NH-4A is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹227 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹227 Cr and has been revised to ₹149 Cr — a cost overrun of -34.2%. Expenditure to date: ₹110 Cr (73.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Balance work of 2L PS from Km 30.800 to Km 70.800 and 2L wi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618942. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of 2L PS from Km 30.800 to Km 70.800 and 2L wi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.