Original Cost
₹227 Cr
Baseline estimate
Revised Cost
₹149 Cr
Latest approved cost
Expenditure
₹110 Cr
Spent to date
Utilization
73.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹39 Cr
Budget left
Spent
₹110 Cr
Remaining
₹39 Cr
Total
₹149 Cr
Project Approved
Construction / Implementation
Original End Date
21/05/2024
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹227 Cr — no cost escalation recorded.
Expenditure stands at ₹110 Cr, which is 73.8% of the revised project cost.
Remaining budget: ₹39 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.