Roads & HighwaysIPM · Central Project +55.8% overrun#618861

Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹1397 CrUtilization: 65.4%Overrun: +₹500 Cr

Original Cost

₹897 Cr

Baseline estimate

+56% overrun

Revised Cost

₹1397 Cr

Latest approved cost

Expenditure

₹914 Cr

Spent to date

Utilization

65.4%

Of revised budget

Escalated

Cost Status

+55.8%

+₹500 Cr increase

Remaining

₹483 Cr

Budget left

Budget Utilization

65.4%
0%25%50%75%100%

Spent

₹914 Cr

Remaining

₹483 Cr

Total

₹1397 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹897 Cr

Revised Cost

₹1397 Cr

Increase

+₹500 Cr

Escalation

+55.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

11/07/2023

Revised Completion

30/09/2026

Completed

Project Details

Project Code618861
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹897 Cr
Revised Cost₹1397 Cr
Expenditure₹914 Cr
Original End Date11/07/2023
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹500 Cr (55.8%) from the original estimate of ₹897 Cr.

Expenditure stands at ₹914 Cr, which is 65.4% of the revised project cost.

Remaining budget: ₹483 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹897.00 Cr, later revised to ₹1397.47 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630"?
Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹897 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹897 Cr and has been revised to ₹1397 Cr — a cost overrun of +55.8%. Expenditure to date: ₹914 Cr (65.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618861. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.