54.405 to km.101.630
Original Cost
₹897 Cr
Baseline estimate
Revised Cost
₹1397 Cr
Latest approved cost
Expenditure
₹897 Cr
Spent to date
Utilization
64.2%
Of revised cost
Cost Overrun
+55.8%
+₹500 Cr
Remaining
₹500 Cr
Budget left
Spent
₹897 Cr
Remaining
₹500 Cr
Total
₹1397 Cr
64.2%
Utilized
Original Cost
₹897 Cr
Revised Cost
₹1397 Cr
Increase
+₹500 Cr
Escalation
+55.8%
Project Approved
Construction / Implementation
Original End Date
2023-07-11
Revised Completion
2026-05-31
Completed
Cost has increased by ₹500 Cr (55.8%) from the original estimate of ₹897 Cr.
Expenditure stands at ₹897 Cr, which is 64.2% of the revised project cost.
Remaining budget: ₹500 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.