Bahraich - Nanpara - Nepalganj Road Gauge Conversion
Original Cost
₹950 Cr
Baseline estimate
Revised Cost
₹550 Cr
Latest approved cost
Expenditure
₹507 Cr
Spent to date
Utilization
92.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹43 Cr
Budget left
Budget Utilization
92.2%Spent
₹507 Cr
Remaining
₹43 Cr
Total
₹550 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/07/2025
Revised Completion
30/09/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹950 Cr — no cost escalation recorded.
Expenditure stands at ₹507 Cr, which is 92.2% of the revised project cost.
Remaining budget: ₹43 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Bahraich - Nanpara - Nepalganj Road Gauge Conversion is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹950.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Bahraich - Nanpara - Nepalganj Road Gauge Conversion"?
- Bahraich - Nanpara - Nepalganj Road Gauge Conversion is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹950 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹950 Cr and has been revised to ₹550 Cr — a cost overrun of -42.1%. Expenditure to date: ₹507 Cr (92.2% of revised cost). Data as of 2025-09.
- QWhich ministry is responsible for this project?
- Bahraich - Nanpara - Nepalganj Road Gauge Conversion is under the Ministry of Railways in the Railways sector. Project code: 705863. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bahraich - Nanpara - Nepalganj Road Gauge Conversion is one of several Bihar projects tracked under the Railways sector on the IPM system.