RailwaysIPM · Central Project +63.3% overrun#705368

Araria-Supaul 92 km

Ministry of RailwaysBihar
Revised Cost: ₹2621 CrUtilization: 83.2%Overrun: +₹1016 Cr

Original Cost

₹1605 Cr

Baseline estimate

+63% overrun

Revised Cost

₹2621 Cr

Latest approved cost

Expenditure

₹2180 Cr

Spent to date

Utilization

83.2%

Of revised budget

Escalated

Cost Status

+63.3%

+₹1016 Cr increase

Remaining

₹441 Cr

Budget left

Budget Utilization

83.2%
0%25%50%75%100%

Spent

₹2180 Cr

Remaining

₹441 Cr

Total

₹2621 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1605 Cr

Revised Cost

₹2621 Cr

Increase

+₹1016 Cr

Escalation

+63.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2024

Revised Completion

31/01/2027

Completed

Project Details

Project Code705368
SectorRailways
MinistryMinistry of Railways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹1605 Cr
Revised Cost₹2621 Cr
Expenditure₹2180 Cr
Original End Date31/03/2024
Revised Date31/01/2027

Project Intelligence

Cost has increased by ₹1016 Cr (63.3%) from the original estimate of ₹1605 Cr.

Expenditure stands at ₹2180 Cr, which is 83.2% of the revised project cost.

Remaining budget: ₹441 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Araria-Supaul 92 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1605.00 Cr, later revised to ₹2621.05 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Araria-Supaul 92 km"?
Araria-Supaul 92 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Bihar. Original cost: ₹1605 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1605 Cr and has been revised to ₹2621 Cr — a cost overrun of +63.3%. Expenditure to date: ₹2180 Cr (83.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Araria-Supaul 92 km is under the Ministry of Railways in the Railways sector. Project code: 705368. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Araria-Supaul 92 km is one of several Bihar projects tracked under the Railways sector on the IPM system.