RailwaysIPM · Central Project +5.2% overrun#705583

Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km

Ministry of RailwaysDelhi
Revised Cost: ₹702 CrUtilization: 57.1%Overrun: +₹35 Cr

Original Cost

₹667 Cr

Baseline estimate

+5% overrun

Revised Cost

₹702 Cr

Latest approved cost

Expenditure

₹401 Cr

Spent to date

Utilization

57.1%

Of revised budget

Escalated

Cost Status

+5.2%

+₹35 Cr increase

Remaining

₹301 Cr

Budget left

Budget Utilization

57.1%
0%25%50%75%100%

Spent

₹401 Cr

Remaining

₹301 Cr

Total

₹702 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹667 Cr

Revised Cost

₹702 Cr

Increase

+₹35 Cr

Escalation

+5.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2023

Revised Completion

31/12/2027

Completed

Project Details

Project Code705583
SectorRailways
MinistryMinistry of Railways
StateDelhi
Data Month2026-08

Financial Summary

Original Cost₹667 Cr
Revised Cost₹702 Cr
Expenditure₹401 Cr
Original End Date31/03/2023
Revised Date31/12/2027

Project Intelligence

Cost has increased by ₹35 Cr (5.2%) from the original estimate of ₹667 Cr.

Expenditure stands at ₹401 Cr, which is 57.1% of the revised project cost.

Remaining budget: ₹301 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. This work is part of the development of Delhi Railway — central government project titles use official ministry terminology rather than the common name. The original approved cost is ₹667.00 Cr, later revised to ₹701.88 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km"?
Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Delhi. Original cost: ₹667 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹667 Cr and has been revised to ₹702 Cr — a cost overrun of +5.2%. Expenditure to date: ₹401 Cr (57.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km is under the Ministry of Railways in the Railways sector. Project code: 705583. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km is one of several Bihar projects tracked under the Railways sector on the IPM system.
QIs this the Delhi Railway project?
Yes — "Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km" is the official DPIIT/IPM project title covering Delhi Railway development works. Central government project titles use official ministry terminology rather than the site's common name.