RailwaysIPM · Central Project#705918

Allahabad division - Aligarh - Harduaganj Flyover

Ministry of RailwaysUttar Pradesh
Revised Cost: ₹1457 CrUtilization: 27.5%

Original Cost

₹1457 Cr

Baseline estimate

On budget

Revised Cost

₹1457 Cr

Latest approved cost

Expenditure

₹400 Cr

Spent to date

Utilization

27.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1057 Cr

Budget left

Budget Utilization

27.5%
0%25%50%75%100%

Spent

₹400 Cr

Remaining

₹1057 Cr

Total

₹1457 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/10/2026

Revised Completion

31/03/2027

Completed

Project Details

Project Code705918
SectorRailways
MinistryMinistry of Railways
StateUttar Pradesh
Data Month2026-06

Financial Summary

Original Cost₹1457 Cr
Revised Cost₹1457 Cr
Expenditure₹400 Cr
Original End Date30/10/2026
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹1457 Cr — no cost escalation recorded.

Expenditure stands at ₹400 Cr, which is 27.5% of the revised project cost.

Remaining budget: ₹1057 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Allahabad division - Aligarh - Harduaganj Flyover is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1457.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Allahabad division - Aligarh - Harduaganj Flyover"?
Allahabad division - Aligarh - Harduaganj Flyover is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹1457 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1457 Cr has not been significantly revised. Expenditure: ₹400 Cr (27.5% of cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Allahabad division - Aligarh - Harduaganj Flyover is under the Ministry of Railways in the Railways sector. Project code: 705918. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Allahabad division - Aligarh - Harduaganj Flyover is one of several Bihar projects tracked under the Railways sector on the IPM system.