Aligarh-Daud Khan - 3rd line 6.9 km & construction of flyover at Daud Khan
Original Cost
₹758 Cr
Baseline estimate
Revised Cost
₹779 Cr
Latest approved cost
Expenditure
₹395 Cr
Spent to date
Utilization
50.7%
Of revised budget
Cost Status
+2.8%
+₹21 Cr increase
Remaining
₹384 Cr
Budget left
Budget Utilization
50.7%Spent
₹395 Cr
Remaining
₹384 Cr
Total
₹779 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹758 Cr
Revised Cost
₹779 Cr
Increase
+₹21 Cr
Escalation
+2.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/01/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹21 Cr (2.8%) from the original estimate of ₹758 Cr.
Expenditure stands at ₹395 Cr, which is 50.7% of the revised project cost.
Remaining budget: ₹384 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Aligarh-Daud Khan - 3rd line 6.9 km & construction of flyover at Daud Khan is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹758.00 Cr, later revised to ₹779.49 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Aligarh-Daud Khan - 3rd line 6.9 km & construction of flyover at Daud Khan"?
- Aligarh-Daud Khan - 3rd line 6.9 km & construction of flyover at Daud Khan is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹758 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹758 Cr and has been revised to ₹779 Cr — a cost overrun of +2.8%. Expenditure to date: ₹395 Cr (50.7% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Aligarh-Daud Khan - 3rd line 6.9 km & construction of flyove is under the Ministry of Railways in the Railways sector. Project code: 705774. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Aligarh-Daud Khan - 3rd line 6.9 km & construction of flyove is one of several Bihar projects tracked under the Railways sector on the IPM system.