Ajmer-Chanderiya section 178.28 km Umbrella work PB57/2019-20/NR
Original Cost
₹1635 Cr
Baseline estimate
Revised Cost
₹1635 Cr
Latest approved cost
Expenditure
₹560 Cr
Spent to date
Utilization
34.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1075 Cr
Budget left
Budget Utilization
34.3%Spent
₹560 Cr
Remaining
₹1075 Cr
Total
₹1635 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/06/2027
Revised Completion
31/03/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1635 Cr — no cost escalation recorded.
Expenditure stands at ₹560 Cr, which is 34.3% of the revised project cost.
Remaining budget: ₹1075 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Ajmer-Chanderiya section 178.28 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1635.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Ajmer-Chanderiya section 178.28 km Umbrella work PB57/2019-20/NR"?
- Ajmer-Chanderiya section 178.28 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Rajasthan. Original cost: ₹1635 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1635 Cr has not been significantly revised. Expenditure: ₹560 Cr (34.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Ajmer-Chanderiya section 178.28 km Umbrella work PB57/2019-2 is under the Ministry of Railways in the Railways sector. Project code: 616843. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Ajmer-Chanderiya section 178.28 km Umbrella work PB57/2019-2 is one of several Bihar projects tracked under the Railways sector on the IPM system.