Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone]
Original Cost
₹1034 Cr
Baseline estimate
Revised Cost
₹1155 Cr
Latest approved cost
Expenditure
₹1126 Cr
Spent to date
Utilization
97.4%
Of revised budget
Cost Status
+11.7%
+₹121 Cr increase
Remaining
₹30 Cr
Budget left
Budget Utilization
97.4%Spent
₹1126 Cr
Remaining
₹30 Cr
Total
₹1155 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1034 Cr
Revised Cost
₹1155 Cr
Increase
+₹121 Cr
Escalation
+11.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/07/2023
Revised Completion
31/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹121 Cr (11.7%) from the original estimate of ₹1034 Cr.
Expenditure stands at ₹1126 Cr, which is 97.4% of the revised project cost.
Remaining budget: ₹30 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1034.00 Cr, later revised to ₹1155.41 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Star"?
- Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1034 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1034 Cr and has been revised to ₹1155 Cr — a cost overrun of +11.7%. Expenditure to date: ₹1126 Cr (97.4% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vej is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618503. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vej is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.