Roads & HighwaysIPM · Central Project +11.7% overrun#618503

Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone]

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1155 CrUtilization: 97.4%Overrun: +₹121 Cr

Original Cost

₹1034 Cr

Baseline estimate

+12% overrun

Revised Cost

₹1155 Cr

Latest approved cost

Expenditure

₹1126 Cr

Spent to date

Utilization

97.4%

Of revised budget

Escalated

Cost Status

+11.7%

+₹121 Cr increase

Remaining

₹30 Cr

Budget left

Budget Utilization

97.4%
0%25%50%75%100%

Spent

₹1126 Cr

Remaining

₹30 Cr

Total

₹1155 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1034 Cr

Revised Cost

₹1155 Cr

Increase

+₹121 Cr

Escalation

+11.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

19/07/2023

Revised Completion

31/08/2026

Completed

Project Details

Project Code618503
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-07

Financial Summary

Original Cost₹1034 Cr
Revised Cost₹1155 Cr
Expenditure₹1126 Cr
Original End Date19/07/2023
Revised Date31/08/2026

Project Intelligence

Cost has increased by ₹121 Cr (11.7%) from the original estimate of ₹1034 Cr.

Expenditure stands at ₹1126 Cr, which is 97.4% of the revised project cost.

Remaining budget: ₹30 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1034.00 Cr, later revised to ₹1155.41 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Star"?
Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1034 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1034 Cr and has been revised to ₹1155 Cr — a cost overrun of +11.7%. Expenditure to date: ₹1126 Cr (97.4% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vej is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618503. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vej is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.