Original Cost
₹1034 Cr
Baseline estimate
Revised Cost
₹1155 Cr
Latest approved cost
Expenditure
₹1010 Cr
Spent to date
Utilization
87.4%
Of revised budget
Cost Status
+11.7%
+₹121 Cr increase
Remaining
₹146 Cr
Budget left
Spent
₹1010 Cr
Remaining
₹146 Cr
Total
₹1155 Cr
Original Cost
₹1034 Cr
Revised Cost
₹1155 Cr
Increase
+₹121 Cr
Escalation
+11.7%
Project Approved
Construction / Implementation
Original End Date
19/07/2023
Revised Completion
30/06/2026
Completed
Cost has increased by ₹121 Cr (11.7%) from the original estimate of ₹1034 Cr.
Expenditure stands at ₹1010 Cr, which is 87.4% of the revised project cost.
Remaining budget: ₹146 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.