Roads & HighwaysIPM · Central Project +9.5% overrun#618501

Ahmedabad - Dholera Pkg I from km. 0.00 to km. 22.00 [Sardar Patel Ring Road - Sindhrej Village]

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1421 CrUtilization: 72.1%Overrun: +₹123 Cr

Original Cost

₹1298 Cr

Baseline estimate

+10% overrun

Revised Cost

₹1421 Cr

Latest approved cost

Expenditure

₹1025 Cr

Spent to date

Utilization

72.1%

Of revised budget

Escalated

Cost Status

+9.5%

+₹123 Cr increase

Remaining

₹396 Cr

Budget left

Budget Utilization

72.1%
0%25%50%75%100%

Spent

₹1025 Cr

Remaining

₹396 Cr

Total

₹1421 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1298 Cr

Revised Cost

₹1421 Cr

Increase

+₹123 Cr

Escalation

+9.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/01/2024

Revised Completion

30/06/2026

Completed

Project Details

Project Code618501
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-05

Financial Summary

Original Cost₹1298 Cr
Revised Cost₹1421 Cr
Expenditure₹1025 Cr
Original End Date10/01/2024
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹123 Cr (9.5%) from the original estimate of ₹1298 Cr.

Expenditure stands at ₹1025 Cr, which is 72.1% of the revised project cost.

Remaining budget: ₹396 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Ahmedabad - Dholera Pkg I from km. 0.00 to km. 22.00 [Sardar Patel Ring Road - Sindhrej Village] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1298.00 Cr, later revised to ₹1421.05 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Ahmedabad - Dholera Pkg I from km. 0.00 to km. 22.00 [Sardar Patel Ring Road - S"?
Ahmedabad - Dholera Pkg I from km. 0.00 to km. 22.00 [Sardar Patel Ring Road - Sindhrej Village] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1298 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1298 Cr and has been revised to ₹1421 Cr — a cost overrun of +9.5%. Expenditure to date: ₹1025 Cr (72.1% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Ahmedabad - Dholera Pkg I from km. 0.00 to km. 22.00 [Sardar is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618501. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Ahmedabad - Dholera Pkg I from km. 0.00 to km. 22.00 [Sardar is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.