Original Cost
₹1554 Cr
Baseline estimate
Revised Cost
₹34 Cr
Latest approved cost
Expenditure
₹28 Cr
Spent to date
Utilization
82.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹6 Cr
Budget left
Spent
₹28 Cr
Remaining
₹6 Cr
Total
₹34 Cr
Project Approved
Construction / Implementation
Original End Date
27/12/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1554 Cr — no cost escalation recorded.
Expenditure stands at ₹28 Cr, which is 82.3% of the revised project cost.
Remaining budget: ₹6 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.