Roads & HighwaysIPM · Central Project#618564

6L with PS of Samakhiyali to Santalpur section from km. 339.700 to Km. 430.100 of NH-27

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹34 CrUtilization: 84.8%

Original Cost

₹1554 Cr

Baseline estimate

On budget

Revised Cost

₹34 Cr

Latest approved cost

Expenditure

₹29 Cr

Spent to date

Utilization

84.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹5 Cr

Budget left

Budget Utilization

84.8%
0%25%50%75%100%

Spent

₹29 Cr

Remaining

₹5 Cr

Total

₹34 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/12/2025

Revised Completion

31/03/2027

Completed

Project Details

Project Code618564
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹1554 Cr
Revised Cost₹34 Cr
Expenditure₹29 Cr
Original End Date27/12/2025
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹1554 Cr — no cost escalation recorded.

Expenditure stands at ₹29 Cr, which is 84.8% of the revised project cost.

Remaining budget: ₹5 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L with PS of Samakhiyali to Santalpur section from km. 339.700 to Km. 430.100 of NH-27 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1554.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L with PS of Samakhiyali to Santalpur section from km. 339.700 to Km. 430.100 o"?
6L with PS of Samakhiyali to Santalpur section from km. 339.700 to Km. 430.100 of NH-27 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1554 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1554 Cr and has been revised to ₹34 Cr — a cost overrun of -97.8%. Expenditure to date: ₹29 Cr (84.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L with PS of Samakhiyali to Santalpur section from km. 339. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618564. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L with PS of Samakhiyali to Santalpur section from km. 339. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.