Original Cost
₹1399 Cr
Baseline estimate
Revised Cost
₹966 Cr
Latest approved cost
Expenditure
₹335 Cr
Spent to date
Utilization
34.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹631 Cr
Budget left
Spent
₹335 Cr
Remaining
₹631 Cr
Total
₹966 Cr
Project Approved
Construction / Implementation
Original End Date
19/10/2025
Revised Completion
31/10/2027
Completed
Project is within original budget of ₹1399 Cr — no cost escalation recorded.
Expenditure stands at ₹335 Cr, which is 34.7% of the revised project cost.
Remaining budget: ₹631 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.