Roads & HighwaysIPM · Central Project#618601

6L of Kappirikkad to Thalikulam section from km 335.85 to km 369.015 of NH - 66 old NH-17

Ministry of Road Transport & HighwaysKerala
Revised Cost: ₹4226 CrUtilization: 79.2%

Original Cost

₹4226 Cr

Baseline estimate

On budget

Revised Cost

₹4226 Cr

Latest approved cost

Expenditure

₹3345 Cr

Spent to date

Utilization

79.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹880 Cr

Budget left

Budget Utilization

79.2%
0%25%50%75%100%

Spent

₹3345 Cr

Remaining

₹880 Cr

Total

₹4226 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/01/2025

Revised Completion

30/06/2027

Completed

Project Details

Project Code618601
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKerala
Data Month2026-08

Financial Summary

Original Cost₹4226 Cr
Revised Cost₹4226 Cr
Expenditure₹3345 Cr
Original End Date26/01/2025
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹4226 Cr — no cost escalation recorded.

Expenditure stands at ₹3345 Cr, which is 79.2% of the revised project cost.

Remaining budget: ₹880 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Kappirikkad to Thalikulam section from km 335.85 to km 369.015 of NH - 66 old NH-17 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹4226.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Kappirikkad to Thalikulam section from km 335.85 to km 369.015 of NH - 66"?
6L of Kappirikkad to Thalikulam section from km 335.85 to km 369.015 of NH - 66 old NH-17 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Kerala. Original cost: ₹4226 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹4226 Cr has not been significantly revised. Expenditure: ₹3345 Cr (79.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L of Kappirikkad to Thalikulam section from km 335.85 to k is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618601. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Kappirikkad to Thalikulam section from km 335.85 to k is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.