Roads & HighwaysIPM · Central Project#618514

6L of Kagal-Satara section from Km 658.000 to Km 725.000 of NH-48 Pkg-II

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹317 CrUtilization: 65.1%

Original Cost

₹2331 Cr

Baseline estimate

On budget

Revised Cost

₹317 Cr

Latest approved cost

Expenditure

₹207 Cr

Spent to date

Utilization

65.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹111 Cr

Budget left

Budget Utilization

65.1%
0%25%50%75%100%

Spent

₹207 Cr

Remaining

₹111 Cr

Total

₹317 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/12/2024

Revised Completion

31/12/2026

Completed

Project Details

Project Code618514
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹2331 Cr
Revised Cost₹317 Cr
Expenditure₹207 Cr
Original End Date15/12/2024
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹2331 Cr — no cost escalation recorded.

Expenditure stands at ₹207 Cr, which is 65.1% of the revised project cost.

Remaining budget: ₹111 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Kagal-Satara section from Km 658.000 to Km 725.000 of NH-48 Pkg-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2331.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Kagal-Satara section from Km 658.000 to Km 725.000 of NH-48 Pkg-II"?
6L of Kagal-Satara section from Km 658.000 to Km 725.000 of NH-48 Pkg-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹2331 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2331 Cr and has been revised to ₹317 Cr — a cost overrun of -86.4%. Expenditure to date: ₹207 Cr (65.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L of Kagal-Satara section from Km 658.000 to Km 725.000 of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618514. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Kagal-Satara section from Km 658.000 to Km 725.000 of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.