Original Cost
₹1525 Cr
Baseline estimate
Revised Cost
₹1937 Cr
Latest approved cost
Expenditure
₹1690 Cr
Spent to date
Utilization
87.3%
Of revised budget
Cost Status
+27.0%
+₹412 Cr increase
Remaining
₹247 Cr
Budget left
Spent
₹1690 Cr
Remaining
₹247 Cr
Total
₹1937 Cr
Original Cost
₹1525 Cr
Revised Cost
₹1937 Cr
Increase
+₹412 Cr
Escalation
+27.0%
Project Approved
Construction / Implementation
Original End Date
09/10/2024
Revised Completion
30/06/2025
Completed
Cost has increased by ₹412 Cr (27.0%) from the original estimate of ₹1525 Cr.
Expenditure stands at ₹1690 Cr, which is 87.3% of the revised project cost.
Remaining budget: ₹247 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.