Original Cost
₹478 Cr
Baseline estimate
Revised Cost
₹638 Cr
Latest approved cost
Expenditure
₹298 Cr
Spent to date
Utilization
46.7%
Of revised budget
Cost Status
+33.5%
+₹160 Cr increase
Remaining
₹340 Cr
Budget left
Spent
₹298 Cr
Remaining
₹340 Cr
Total
₹638 Cr
Original Cost
₹478 Cr
Revised Cost
₹638 Cr
Increase
+₹160 Cr
Escalation
+33.5%
Project Approved
Construction / Implementation
Original End Date
23/03/2024
Revised Completion
30/04/2026
Completed
Cost has increased by ₹160 Cr (33.5%) from the original estimate of ₹478 Cr.
Expenditure stands at ₹298 Cr, which is 46.7% of the revised project cost.
Remaining budget: ₹340 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.