Roads & HighwaysIPM · Central Project +33.5% overrun#618676

6L of Dhanara - Hatibena Section from Km 124.611 to km 146.50 of NH-130-CD Package OD-1

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹638 CrUtilization: 46.7%Overrun: +₹160 Cr

Original Cost

₹478 Cr

Baseline estimate

+34% overrun

Revised Cost

₹638 Cr

Latest approved cost

Expenditure

₹298 Cr

Spent to date

Utilization

46.7%

Of revised budget

Escalated

Cost Status

+33.5%

+₹160 Cr increase

Remaining

₹340 Cr

Budget left

Budget Utilization

46.7%
0%25%50%75%100%

Spent

₹298 Cr

Remaining

₹340 Cr

Total

₹638 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹478 Cr

Revised Cost

₹638 Cr

Increase

+₹160 Cr

Escalation

+33.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

23/03/2024

Revised Completion

30/04/2026

Completed

Project Details

Project Code618676
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-05

Financial Summary

Original Cost₹478 Cr
Revised Cost₹638 Cr
Expenditure₹298 Cr
Original End Date23/03/2024
Revised Date30/04/2026

Project Intelligence

Cost has increased by ₹160 Cr (33.5%) from the original estimate of ₹478 Cr.

Expenditure stands at ₹298 Cr, which is 46.7% of the revised project cost.

Remaining budget: ₹340 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Dhanara - Hatibena Section from Km 124.611 to km 146.50 of NH-130-CD Package OD-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹478.00 Cr, later revised to ₹638.32 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Dhanara - Hatibena Section from Km 124.611 to km 146.50 of NH-130-CD Pack"?
6L of Dhanara - Hatibena Section from Km 124.611 to km 146.50 of NH-130-CD Package OD-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹478 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹478 Cr and has been revised to ₹638 Cr — a cost overrun of +33.5%. Expenditure to date: ₹298 Cr (46.7% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
6L of Dhanara - Hatibena Section from Km 124.611 to km 146. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618676. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Dhanara - Hatibena Section from Km 124.611 to km 146. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.