6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.595 of NH-8Package-VII
Original Cost
₹357 Cr
Baseline estimate
Revised Cost
₹463 Cr
Latest approved cost
Expenditure
₹104 Cr
Spent to date
Utilization
22.5%
Of revised budget
Cost Status
+29.7%
+₹106 Cr increase
Remaining
₹359 Cr
Budget left
Budget Utilization
22.5%Spent
₹104 Cr
Remaining
₹359 Cr
Total
₹463 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹357 Cr
Revised Cost
₹463 Cr
Increase
+₹106 Cr
Escalation
+29.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
10/05/2019
Revised Completion
30/06/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹106 Cr (29.7%) from the original estimate of ₹357 Cr.
Expenditure stands at ₹104 Cr, which is 22.5% of the revised project cost.
Remaining budget: ₹359 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.595 of NH-8Package-VII is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹357.00 Cr, later revised to ₹463.03 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.595 of NH-8Package-VII"?
- 6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.595 of NH-8Package-VII is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹357 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹357 Cr and has been revised to ₹463 Cr — a cost overrun of +29.7%. Expenditure to date: ₹104 Cr (22.5% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- 6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.59 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619067. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.59 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.