Roads & HighwaysIPM · Central Project#619075

6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹633 CrUtilization: 8.3%

Original Cost

₹639 Cr

Baseline estimate

On budget

Revised Cost

₹633 Cr

Latest approved cost

Expenditure

₹52 Cr

Spent to date

Utilization

8.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹581 Cr

Budget left

Budget Utilization

8.3%
0%25%50%75%100%

Spent

₹52 Cr

Remaining

₹581 Cr

Total

₹633 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/06/2014

Revised Completion

07/05/2026

Completed

Project Details

Project Code619075
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-05

Financial Summary

Original Cost₹639 Cr
Revised Cost₹633 Cr
Expenditure₹52 Cr
Original End Date10/06/2014
Revised Date07/05/2026

Project Intelligence

Project is within original budget of ₹639 Cr — no cost escalation recorded.

Expenditure stands at ₹52 Cr, which is 8.3% of the revised project cost.

Remaining budget: ₹581 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹639.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16"?
6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹639 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹639 Cr and has been revised to ₹633 Cr — a cost overrun of -1%. Expenditure to date: ₹52 Cr (8.3% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619075. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.