Roads & HighwaysIPM · Central Project#618532

6L of Aurangabad to Bihar-Jharkhand border Chordaha section from km. 209.827 to Km. 249.525 of NH-19 PKG-02

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹738 CrUtilization: 82.0%

Original Cost

₹1822 Cr

Baseline estimate

On budget

Revised Cost

₹738 Cr

Latest approved cost

Expenditure

₹606 Cr

Spent to date

Utilization

82.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹133 Cr

Budget left

Budget Utilization

82.0%
0%25%50%75%100%

Spent

₹606 Cr

Remaining

₹133 Cr

Total

₹738 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/03/2024

Revised Completion

15/05/2026

Completed

Project Details

Project Code618532
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-05

Financial Summary

Original Cost₹1822 Cr
Revised Cost₹738 Cr
Expenditure₹606 Cr
Original End Date27/03/2024
Revised Date15/05/2026

Project Intelligence

Project is within original budget of ₹1822 Cr — no cost escalation recorded.

Expenditure stands at ₹606 Cr, which is 82.0% of the revised project cost.

Remaining budget: ₹133 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Aurangabad to Bihar-Jharkhand border Chordaha section from km. 209.827 to Km. 249.525 of NH-19 PKG-02 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1822.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Aurangabad to Bihar-Jharkhand border Chordaha section from km. 209.827 to"?
6L of Aurangabad to Bihar-Jharkhand border Chordaha section from km. 209.827 to Km. 249.525 of NH-19 PKG-02 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹1822 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1822 Cr and has been revised to ₹738 Cr — a cost overrun of -59.5%. Expenditure to date: ₹606 Cr (82.0% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
6L of Aurangabad to Bihar-Jharkhand border Chordaha section is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618532. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Aurangabad to Bihar-Jharkhand border Chordaha section is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.