209.827 to Km. 249.525 of NH-19 PKG-02
Original Cost
₹1822 Cr
Baseline estimate
Revised Cost
₹738 Cr
Latest approved cost
Expenditure
₹606 Cr
Spent to date
Utilization
82.0%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹133 Cr
Budget left
Spent
₹606 Cr
Remaining
₹133 Cr
Total
₹738 Cr
82.0%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-03-27
Revised Completion
2026-05-15
Completed
Project is within original budget of ₹1822 Cr — no cost escalation recorded.
Expenditure stands at ₹606 Cr, which is 82.0% of the revised project cost.
Remaining budget: ₹133 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.