180.000 to km. 209.827 of NH-2 PKG-01
Original Cost
₹1054 Cr
Baseline estimate
Revised Cost
₹787 Cr
Latest approved cost
Expenditure
₹111 Cr
Spent to date
Utilization
14.1%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹676 Cr
Budget left
Spent
₹111 Cr
Remaining
₹676 Cr
Total
₹787 Cr
14.1%
Utilized
Project Approved
Construction / Implementation
Original End Date
2026-12-17
Revised Completion
2026-12-17
Completed
Project is within original budget of ₹1054 Cr — no cost escalation recorded.
Expenditure stands at ₹111 Cr, which is 14.1% of the revised project cost.
Remaining budget: ₹676 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.