Roads & HighwaysIPM · Central Project +16.0% overrun#619134

6L of Ambala-Chandigarh greenfield section from Km. 0.000 to Km. 25.000 with 4L spur to Lalru from Km. 0.000 to Km. 5.828 & spur to PR-7 road from Km. 0.000 to Km. 11.157

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹1905 CrUtilization: 68.1%Overrun: +₹263 Cr

Original Cost

₹1642 Cr

Baseline estimate

+16% overrun

Revised Cost

₹1905 Cr

Latest approved cost

Expenditure

₹1296 Cr

Spent to date

Utilization

68.1%

Of revised budget

Escalated

Cost Status

+16.0%

+₹263 Cr increase

Remaining

₹608 Cr

Budget left

Budget Utilization

68.1%
0%25%50%75%100%

Spent

₹1296 Cr

Remaining

₹608 Cr

Total

₹1905 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1642 Cr

Revised Cost

₹1905 Cr

Increase

+₹263 Cr

Escalation

+16.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/10/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code619134
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹1642 Cr
Revised Cost₹1905 Cr
Expenditure₹1296 Cr
Original End Date12/10/2025
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹263 Cr (16.0%) from the original estimate of ₹1642 Cr.

Expenditure stands at ₹1296 Cr, which is 68.1% of the revised project cost.

Remaining budget: ₹608 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Ambala-Chandigarh greenfield section from Km. 0.000 to Km. 25.000 with 4L spur to Lalru from Km. 0.000 to Km. 5.828 & spur to PR-7 road from Km. 0.000 to Km. 11.157 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1642.00 Cr, later revised to ₹1904.79 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Ambala-Chandigarh greenfield section from Km. 0.000 to Km. 25.000 with 4L "?
6L of Ambala-Chandigarh greenfield section from Km. 0.000 to Km. 25.000 with 4L spur to Lalru from Km. 0.000 to Km. 5.828 & spur to PR-7 road from Km. 0.000 to Km. 11.157 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1642 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1642 Cr and has been revised to ₹1905 Cr — a cost overrun of +16%. Expenditure to date: ₹1296 Cr (68.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L of Ambala-Chandigarh greenfield section from Km. 0.000 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619134. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Ambala-Chandigarh greenfield section from Km. 0.000 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.