Original Cost
₹1642 Cr
Baseline estimate
Revised Cost
₹1905 Cr
Latest approved cost
Expenditure
₹571 Cr
Spent to date
Utilization
30.0%
Of revised budget
Cost Status
+16.0%
+₹263 Cr increase
Remaining
₹1334 Cr
Budget left
Spent
₹571 Cr
Remaining
₹1334 Cr
Total
₹1905 Cr
Original Cost
₹1642 Cr
Revised Cost
₹1905 Cr
Increase
+₹263 Cr
Escalation
+16.0%
Project Approved
Construction / Implementation
Original End Date
12/10/2025
Revised Completion
30/09/2026
Completed
Cost has increased by ₹263 Cr (16.0%) from the original estimate of ₹1642 Cr.
Expenditure stands at ₹571 Cr, which is 30.0% of the revised project cost.
Remaining budget: ₹1334 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.