6L Greenfield Varanasi- Ranchi- Kolkata Highway from Sonepurbigha village to junction with NH- 22 Chatra Bypass near Chatra from km 184.700 to km 222.000Pkg -8
Original Cost
₹1728 Cr
Baseline estimate
Revised Cost
₹1728 Cr
Latest approved cost
Expenditure
₹205 Cr
Spent to date
Utilization
11.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1523 Cr
Budget left
Budget Utilization
11.8%Spent
₹205 Cr
Remaining
₹1523 Cr
Total
₹1728 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/05/2028
Revised Completion
22/05/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1728 Cr — no cost escalation recorded.
Expenditure stands at ₹205 Cr, which is 11.8% of the revised project cost.
Remaining budget: ₹1523 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L Greenfield Varanasi- Ranchi- Kolkata Highway from Sonepurbigha village to junction with NH- 22 Chatra Bypass near Chatra from km 184.700 to km 222.000Pkg -8 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1728.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L Greenfield Varanasi- Ranchi- Kolkata Highway from Sonepurbigha village to jun"?
- 6L Greenfield Varanasi- Ranchi- Kolkata Highway from Sonepurbigha village to junction with NH- 22 Chatra Bypass near Chatra from km 184.700 to km 222.000Pkg -8 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹1728 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1728 Cr has not been significantly revised. Expenditure: ₹205 Cr (11.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 6L Greenfield Varanasi- Ranchi- Kolkata Highway from Sonepur is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618732. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Greenfield Varanasi- Ranchi- Kolkata Highway from Sonepur is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.