to Konki village From KM. 54.000 to KM. 90.000Pkg-3
Original Cost
₹1577 Cr
Baseline estimate
Revised Cost
₹1711 Cr
Latest approved cost
Expenditure
₹123 Cr
Spent to date
Utilization
7.2%
Of revised cost
Cost Overrun
+8.5%
+₹134 Cr
Remaining
₹1588 Cr
Budget left
Spent
₹123 Cr
Remaining
₹1588 Cr
Total
₹1711 Cr
7.2%
Utilized
Original Cost
₹1577 Cr
Revised Cost
₹1711 Cr
Increase
+₹134 Cr
Escalation
+8.5%
Project Approved
Construction / Implementation
Original End Date
2027-10-05
Revised Completion
2027-10-05
Completed
Cost has increased by ₹134 Cr (8.5%) from the original estimate of ₹1577 Cr.
Expenditure stands at ₹123 Cr, which is 7.2% of the revised project cost.
Remaining budget: ₹1588 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.