6L Greenfield Kanpur - Lucknow Expressway Pkg II from km. 28.500 to km. 73.744
Original Cost
₹2472 Cr
Baseline estimate
Revised Cost
₹2489 Cr
Latest approved cost
Expenditure
₹1179 Cr
Spent to date
Utilization
47.4%
Of revised budget
Cost Status
+0.7%
+₹17 Cr increase
Remaining
₹1310 Cr
Budget left
Budget Utilization
47.4%Spent
₹1179 Cr
Remaining
₹1310 Cr
Total
₹2489 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2472 Cr
Revised Cost
₹2489 Cr
Increase
+₹17 Cr
Escalation
+0.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/05/2025
Revised Completion
10/04/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹17 Cr (0.7%) from the original estimate of ₹2472 Cr.
Expenditure stands at ₹1179 Cr, which is 47.4% of the revised project cost.
Remaining budget: ₹1310 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L Greenfield Kanpur - Lucknow Expressway Pkg II from km. 28.500 to km. 73.744 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2472.00 Cr, later revised to ₹2489.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L Greenfield Kanpur - Lucknow Expressway Pkg II from km. 28.500 to km. 73.744"?
- 6L Greenfield Kanpur - Lucknow Expressway Pkg II from km. 28.500 to km. 73.744 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2472 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2472 Cr and has been revised to ₹2489 Cr — a cost overrun of +0.7%. Expenditure to date: ₹1179 Cr (47.4% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- 6L Greenfield Kanpur - Lucknow Expressway Pkg II from km. 28 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618498. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Greenfield Kanpur - Lucknow Expressway Pkg II from km. 28 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.