Original Cost
₹1389 Cr
Baseline estimate
Revised Cost
₹1067 Cr
Latest approved cost
Expenditure
₹1153 Cr
Spent to date
Utilization
108.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹1153 Cr
Remaining
₹0 Cr
Total
₹1067 Cr
Project Approved
Construction / Implementation
Original End Date
23/04/2025
Revised Completion
30/11/2026
Completed
Project is within original budget of ₹1389 Cr — no cost escalation recorded.
Expenditure stands at ₹1153 Cr, which is 108.1% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.