Roads & HighwaysIPM · Central Project#618808

6L Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of NH-117

Ministry of Road Transport & HighwaysWest Bengal
Revised Cost: ₹1203 CrUtilization: 37.5%

Original Cost

₹1213 Cr

Baseline estimate

On budget

Revised Cost

₹1203 Cr

Latest approved cost

Expenditure

₹452 Cr

Spent to date

Utilization

37.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹752 Cr

Budget left

Budget Utilization

37.5%
0%25%50%75%100%

Spent

₹452 Cr

Remaining

₹752 Cr

Total

₹1203 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/12/2026

Revised Completion

31/12/2027

Completed

Project Details

Project Code618808
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹1213 Cr
Revised Cost₹1203 Cr
Expenditure₹452 Cr
Original End Date03/12/2026
Revised Date31/12/2027

Project Intelligence

Project is within original budget of ₹1213 Cr — no cost escalation recorded.

Expenditure stands at ₹452 Cr, which is 37.5% of the revised project cost.

Remaining budget: ₹752 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of NH-117 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1213.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of NH-117"?
6L Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of NH-117 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹1213 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1213 Cr and has been revised to ₹1203 Cr — a cost overrun of -0.8%. Expenditure to date: ₹452 Cr (37.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of N is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618808. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of N is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.