starting from Km 8.480 near Sherpur to Km 23.000 near Dighwara
Original Cost
₹6292 Cr
Baseline estimate
Revised Cost
₹3352 Cr
Latest approved cost
Expenditure
₹582 Cr
Spent to date
Utilization
17.4%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹2770 Cr
Budget left
Spent
₹582 Cr
Remaining
₹2770 Cr
Total
₹3352 Cr
17.4%
Utilized
Project Approved
Construction / Implementation
Original End Date
2027-09-05
Revised Completion
2029-03-31
Completed
Project is within original budget of ₹6292 Cr — no cost escalation recorded.
Expenditure stands at ₹582 Cr, which is 17.4% of the revised project cost.
Remaining budget: ₹2770 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.