6L Amritsar-Bathinda Greenfield section from village Tiba on NE-5A to Jn. with Moga Jalandhar road NH-703 near Dharamkot from km 0.000 to km 39.000 of NH-754A Pkg-1
Original Cost
₹1229 Cr
Baseline estimate
Revised Cost
₹1549 Cr
Latest approved cost
Expenditure
₹1078 Cr
Spent to date
Utilization
69.6%
Of revised budget
Cost Status
+26.1%
+₹320 Cr increase
Remaining
₹471 Cr
Budget left
Budget Utilization
69.6%Spent
₹1078 Cr
Remaining
₹471 Cr
Total
₹1549 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1229 Cr
Revised Cost
₹1549 Cr
Increase
+₹320 Cr
Escalation
+26.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/11/2024
Revised Completion
14/12/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹320 Cr (26.1%) from the original estimate of ₹1229 Cr.
Expenditure stands at ₹1078 Cr, which is 69.6% of the revised project cost.
Remaining budget: ₹471 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L Amritsar-Bathinda Greenfield section from village Tiba on NE-5A to Jn. with Moga Jalandhar road NH-703 near Dharamkot from km 0.000 to km 39.000 of NH-754A Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1229.00 Cr, later revised to ₹1549.32 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L Amritsar-Bathinda Greenfield section from village Tiba on NE-5A to Jn. with M"?
- 6L Amritsar-Bathinda Greenfield section from village Tiba on NE-5A to Jn. with Moga Jalandhar road NH-703 near Dharamkot from km 0.000 to km 39.000 of NH-754A Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1229 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1229 Cr and has been revised to ₹1549 Cr — a cost overrun of +26.1%. Expenditure to date: ₹1078 Cr (69.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 6L Amritsar-Bathinda Greenfield section from village Tiba on is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618617. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Amritsar-Bathinda Greenfield section from village Tiba on is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.