Original Cost
₹1229 Cr
Baseline estimate
Revised Cost
₹1549 Cr
Latest approved cost
Expenditure
₹773 Cr
Spent to date
Utilization
49.9%
Of revised budget
Cost Status
+26.1%
+₹320 Cr increase
Remaining
₹776 Cr
Budget left
Spent
₹773 Cr
Remaining
₹776 Cr
Total
₹1549 Cr
Original Cost
₹1229 Cr
Revised Cost
₹1549 Cr
Increase
+₹320 Cr
Escalation
+26.1%
Project Approved
Construction / Implementation
Original End Date
13/11/2024
Revised Completion
30/06/2027
Completed
Cost has increased by ₹320 Cr (26.1%) from the original estimate of ₹1229 Cr.
Expenditure stands at ₹773 Cr, which is 49.9% of the revised project cost.
Remaining budget: ₹776 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.