Original Cost
₹2029 Cr
Baseline estimate
Revised Cost
₹2677 Cr
Latest approved cost
Expenditure
₹515 Cr
Spent to date
Utilization
19.2%
Of revised budget
Cost Status
+31.9%
+₹648 Cr increase
Remaining
₹2162 Cr
Budget left
Spent
₹515 Cr
Remaining
₹2162 Cr
Total
₹2677 Cr
Original Cost
₹2029 Cr
Revised Cost
₹2677 Cr
Increase
+₹648 Cr
Escalation
+31.9%
Project Approved
Construction / Implementation
Original End Date
16/06/2026
Revised Completion
21/07/2027
Completed
Cost has increased by ₹648 Cr (31.9%) from the original estimate of ₹2029 Cr.
Expenditure stands at ₹515 Cr, which is 19.2% of the revised project cost.
Remaining budget: ₹2162 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.