Original Cost
₹1216 Cr
Baseline estimate
Revised Cost
₹1242 Cr
Latest approved cost
Expenditure
₹698 Cr
Spent to date
Utilization
56.2%
Of revised budget
Cost Status
+2.1%
+₹26 Cr increase
Remaining
₹544 Cr
Budget left
Spent
₹698 Cr
Remaining
₹544 Cr
Total
₹1242 Cr
Original Cost
₹1216 Cr
Revised Cost
₹1242 Cr
Increase
+₹26 Cr
Escalation
+2.1%
Project Approved
Construction / Implementation
Original End Date
29/03/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹26 Cr (2.1%) from the original estimate of ₹1216 Cr.
Expenditure stands at ₹698 Cr, which is 56.2% of the revised project cost.
Remaining budget: ₹544 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.