Original Cost
₹1228 Cr
Baseline estimate
Revised Cost
₹1316 Cr
Latest approved cost
Expenditure
₹528 Cr
Spent to date
Utilization
40.1%
Of revised budget
Cost Status
+7.2%
+₹88 Cr increase
Remaining
₹788 Cr
Budget left
Spent
₹528 Cr
Remaining
₹788 Cr
Total
₹1316 Cr
Original Cost
₹1228 Cr
Revised Cost
₹1316 Cr
Increase
+₹88 Cr
Escalation
+7.2%
Project Approved
Construction / Implementation
Original End Date
03/01/2025
Revised Completion
30/04/2027
Completed
Cost has increased by ₹88 Cr (7.2%) from the original estimate of ₹1228 Cr.
Expenditure stands at ₹528 Cr, which is 40.1% of the revised project cost.
Remaining budget: ₹788 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.