Original Cost
₹1059 Cr
Baseline estimate
Revised Cost
₹946 Cr
Latest approved cost
Expenditure
₹378 Cr
Spent to date
Utilization
39.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹568 Cr
Budget left
Spent
₹378 Cr
Remaining
₹568 Cr
Total
₹946 Cr
Project Approved
Construction / Implementation
Original End Date
03/02/2026
Revised Completion
30/04/2027
Completed
Project is within original budget of ₹1059 Cr — no cost escalation recorded.
Expenditure stands at ₹378 Cr, which is 39.9% of the revised project cost.
Remaining budget: ₹568 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.