Roads & HighwaysIPM · Central Project#618721

6L Access Controlled Greenfield Highway from Chandrasekharapuram Ch. 228000 to Polavaram Ch. 260000of [NH-544G] Package-11

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹1110 CrUtilization: 32.3%

Original Cost

₹1293 Cr

Baseline estimate

On budget

Revised Cost

₹1110 Cr

Latest approved cost

Expenditure

₹359 Cr

Spent to date

Utilization

32.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹752 Cr

Budget left

Budget Utilization

32.3%
0%25%50%75%100%

Spent

₹359 Cr

Remaining

₹752 Cr

Total

₹1110 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/02/2026

Revised Completion

31/08/2027

Completed

Project Details

Project Code618721
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1293 Cr
Revised Cost₹1110 Cr
Expenditure₹359 Cr
Original End Date10/02/2026
Revised Date31/08/2027

Project Intelligence

Project is within original budget of ₹1293 Cr — no cost escalation recorded.

Expenditure stands at ₹359 Cr, which is 32.3% of the revised project cost.

Remaining budget: ₹752 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L Access Controlled Greenfield Highway from Chandrasekharapuram Ch. 228000 to Polavaram Ch. 260000of [NH-544G] Package-11 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1293.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L Access Controlled Greenfield Highway from Chandrasekharapuram Ch. 228000 to "?
6L Access Controlled Greenfield Highway from Chandrasekharapuram Ch. 228000 to Polavaram Ch. 260000of [NH-544G] Package-11 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹1293 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1293 Cr and has been revised to ₹1110 Cr — a cost overrun of -14.1%. Expenditure to date: ₹359 Cr (32.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L Access Controlled Greenfield Highway from Chandrasekhara is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618721. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Access Controlled Greenfield Highway from Chandrasekhara is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.