Original Cost
₹1335 Cr
Baseline estimate
Revised Cost
₹1335 Cr
Latest approved cost
Expenditure
₹985 Cr
Spent to date
Utilization
73.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹351 Cr
Budget left
Spent
₹985 Cr
Remaining
₹351 Cr
Total
₹1335 Cr
Project Approved
Construction / Implementation
Original End Date
02/09/2024
Revised Completion
14/04/2026
Completed
Project is within original budget of ₹1335 Cr — no cost escalation recorded.
Expenditure stands at ₹985 Cr, which is 73.7% of the revised project cost.
Remaining budget: ₹351 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.