Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /6L access control Greenfield highway of Vill-Lohad
Roads & HighwaysIPM · Central Project#618970

6L access control Greenfield highway of Vill-Lohadda to Vill-Karaunda Mahajan from Km. 27.000 to Km. 56.500 Pkg-2

Ministry of Road Transport & HighwaysUttar PradeshData: 2026-03
Revised Cost: ₹1335 CrUtilization: 73.7%

Original Cost

₹1335 Cr

Baseline estimate

On Budget

Revised Cost

₹1335 Cr

Latest approved cost

Expenditure

₹985 Cr

Spent to date

Utilization

73.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹351 Cr

Budget left

Budget Utilization

73.7%
0%25%50%75%100%

Spent

₹985 Cr

Remaining

₹351 Cr

Total

₹1335 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/09/2024

Revised Completion

14/04/2026

Completed

Project Details

Project Code618970
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-03

Financial & Timeline

Original Cost₹1335 Cr
Revised Cost₹1335 Cr
Expenditure₹985 Cr
Original End Date02/09/2024
Revised Date14/04/2026

Project Intelligence

Project is within original budget of ₹1335 Cr — no cost escalation recorded.

Expenditure stands at ₹985 Cr, which is 73.7% of the revised project cost.

Remaining budget: ₹351 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Frequently Asked Questions

What is IPM project "6L access control Greenfield highway of Vill-Lohadda to Vill-Karaunda Mahajan fr"?
6L access control Greenfield highway of Vill-Lohadda to Vill-Karaunda Mahajan from Km. 27.000 to Km. 56.500 Pkg-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1335 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost of ₹1335 Cr has not been significantly revised. Expenditure: ₹985 Cr (73.7% of cost). Data as of 2026-03.
Which ministry is responsible for this project?
6L access control Greenfield highway of Vill-Lohadda to Vill is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618970. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L access control Greenfield highway of Vill-Lohadda to Vill is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview