Original Cost
₹465 Cr
Baseline estimate
Revised Cost
₹472 Cr
Latest approved cost
Expenditure
₹183 Cr
Spent to date
Utilization
38.7%
Of revised budget
Cost Status
+1.6%
+₹7 Cr increase
Remaining
₹289 Cr
Budget left
Spent
₹183 Cr
Remaining
₹289 Cr
Total
₹472 Cr
Original Cost
₹465 Cr
Revised Cost
₹472 Cr
Increase
+₹7 Cr
Escalation
+1.6%
Project Approved
Construction / Implementation
Original End Date
27/03/2020
Revised Completion
15/06/2026
Completed
Cost has increased by ₹7 Cr (1.6%) from the original estimate of ₹465 Cr.
Expenditure stands at ₹183 Cr, which is 38.7% of the revised project cost.
Remaining budget: ₹289 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.