6 laning of Balance Work of Chennai - Tada from km. 21.40 to km. 54.40
Original Cost
₹465 Cr
Baseline estimate
Revised Cost
₹472 Cr
Latest approved cost
Expenditure
₹390 Cr
Spent to date
Utilization
82.6%
Of revised budget
Cost Status
+1.6%
+₹7 Cr increase
Remaining
₹82 Cr
Budget left
Budget Utilization
82.6%Spent
₹390 Cr
Remaining
₹82 Cr
Total
₹472 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹465 Cr
Revised Cost
₹472 Cr
Increase
+₹7 Cr
Escalation
+1.6%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
27/03/2020
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹7 Cr (1.6%) from the original estimate of ₹465 Cr.
Expenditure stands at ₹390 Cr, which is 82.6% of the revised project cost.
Remaining budget: ₹82 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6 laning of Balance Work of Chennai - Tada from km. 21.40 to km. 54.40 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹465.00 Cr, later revised to ₹472.37 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6 laning of Balance Work of Chennai - Tada from km. 21.40 to km. 54.40"?
- 6 laning of Balance Work of Chennai - Tada from km. 21.40 to km. 54.40 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹465 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹465 Cr and has been revised to ₹472 Cr — a cost overrun of +1.6%. Expenditure to date: ₹390 Cr (82.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 6 laning of Balance Work of Chennai - Tada from km. 21.40 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619077. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6 laning of Balance Work of Chennai - Tada from km. 21.40 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.