4th line - Rajnandgaon-Dongarhgarh 31.2 km PB72/NR/2022-23
Original Cost
₹328 Cr
Baseline estimate
Revised Cost
₹328 Cr
Latest approved cost
Expenditure
₹102 Cr
Spent to date
Utilization
30.9%
Of revised budget
Cost Status
+0.1%
+₹0 Cr increase
Remaining
₹227 Cr
Budget left
Budget Utilization
30.9%Spent
₹102 Cr
Remaining
₹227 Cr
Total
₹328 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹328 Cr
Revised Cost
₹328 Cr
Increase
+₹0 Cr
Escalation
+0.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/01/2027
Revised Completion
31/01/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹0 Cr (0.1%) from the original estimate of ₹328 Cr.
Expenditure stands at ₹102 Cr, which is 30.9% of the revised project cost.
Remaining budget: ₹227 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
4th line - Rajnandgaon-Dongarhgarh 31.2 km PB72/NR/2022-23 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹328.00 Cr, later revised to ₹328.34 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4th line - Rajnandgaon-Dongarhgarh 31.2 km PB72/NR/2022-23"?
- 4th line - Rajnandgaon-Dongarhgarh 31.2 km PB72/NR/2022-23 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Chhattisgarh. Original cost: ₹328 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹328 Cr and has been revised to ₹328 Cr — a cost overrun of +0.1%. Expenditure to date: ₹102 Cr (30.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4th line - Rajnandgaon-Dongarhgarh 31.2 km PB72/NR/2022-23 is under the Ministry of Railways in the Railways sector. Project code: 709818. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4th line - Rajnandgaon-Dongarhgarh 31.2 km PB72/NR/2022-23 is one of several Bihar projects tracked under the Railways sector on the IPM system.