4th line - Bhilai-Bhilai nagar 8.8 km PB72/NR/2022-23
Original Cost
₹177 Cr
Baseline estimate
Revised Cost
₹177 Cr
Latest approved cost
Expenditure
₹39 Cr
Spent to date
Utilization
22.2%
Of revised budget
Cost Status
+0.2%
+₹0 Cr increase
Remaining
₹138 Cr
Budget left
Budget Utilization
22.2%Spent
₹39 Cr
Remaining
₹138 Cr
Total
₹177 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹177 Cr
Revised Cost
₹177 Cr
Increase
+₹0 Cr
Escalation
+0.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
28/02/2027
Revised Completion
28/02/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹0 Cr (0.2%) from the original estimate of ₹177 Cr.
Expenditure stands at ₹39 Cr, which is 22.2% of the revised project cost.
Remaining budget: ₹138 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
4th line - Bhilai-Bhilai nagar 8.8 km PB72/NR/2022-23 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹177.00 Cr, later revised to ₹177.34 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4th line - Bhilai-Bhilai nagar 8.8 km PB72/NR/2022-23"?
- 4th line - Bhilai-Bhilai nagar 8.8 km PB72/NR/2022-23 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹177 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹177 Cr and has been revised to ₹177 Cr — a cost overrun of +0.2%. Expenditure to date: ₹39 Cr (22.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4th line - Bhilai-Bhilai nagar 8.8 km PB72/NR/2022-23 is under the Ministry of Railways in the Railways sector. Project code: 709816. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4th line - Bhilai-Bhilai nagar 8.8 km PB72/NR/2022-23 is one of several Bihar projects tracked under the Railways sector on the IPM system.