Original Cost
₹626 Cr
Baseline estimate
Revised Cost
₹284 Cr
Latest approved cost
Expenditure
₹112 Cr
Spent to date
Utilization
39.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹172 Cr
Budget left
Spent
₹112 Cr
Remaining
₹172 Cr
Total
₹284 Cr
Project Approved
Construction / Implementation
Original End Date
31/07/2026
Revised Completion
31/07/2027
Completed
Project is within original budget of ₹626 Cr — no cost escalation recorded.
Expenditure stands at ₹112 Cr, which is 39.4% of the revised project cost.
Remaining budget: ₹172 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.