Original Cost
₹1140 Cr
Baseline estimate
Revised Cost
₹1155 Cr
Latest approved cost
Expenditure
₹7 Cr
Spent to date
Utilization
0.6%
Of revised budget
Cost Status
+1.3%
+₹15 Cr increase
Remaining
₹1148 Cr
Budget left
Spent
₹7 Cr
Remaining
₹1148 Cr
Total
₹1155 Cr
Original Cost
₹1140 Cr
Revised Cost
₹1155 Cr
Increase
+₹15 Cr
Escalation
+1.3%
Project Approved
Construction / Implementation
Original End Date
09/12/2019
Revised Completion
Completed
Cost has increased by ₹15 Cr (1.3%) from the original estimate of ₹1140 Cr.
Expenditure stands at ₹7 Cr, which is 0.6% of the revised project cost.
Remaining budget: ₹1148 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.