Original Cost
₹191 Cr
Baseline estimate
Revised Cost
₹192 Cr
Latest approved cost
Expenditure
₹182 Cr
Spent to date
Utilization
94.8%
Of revised budget
Cost Status
+0.6%
+₹1 Cr increase
Remaining
₹10 Cr
Budget left
Spent
₹182 Cr
Remaining
₹10 Cr
Total
₹192 Cr
Original Cost
₹191 Cr
Revised Cost
₹192 Cr
Increase
+₹1 Cr
Escalation
+0.6%
Project Approved
Construction / Implementation
Original End Date
14/06/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹1 Cr (0.6%) from the original estimate of ₹191 Cr.
Expenditure stands at ₹182 Cr, which is 94.8% of the revised project cost.
Remaining budget: ₹10 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.