of Manikpur-Sahebganj of NH-139W
Original Cost
₹1539 Cr
Baseline estimate
Revised Cost
₹1539 Cr
Latest approved cost
Expenditure
₹95 Cr
Spent to date
Utilization
6.2%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹1444 Cr
Budget left
Spent
₹95 Cr
Remaining
₹1444 Cr
Total
₹1539 Cr
6.2%
Utilized
Project Approved
Construction / Implementation
Original End Date
2027-12-31
Revised Completion
2027-12-31
Completed
Project is within original budget of ₹1539 Cr — no cost escalation recorded.
Expenditure stands at ₹95 Cr, which is 6.2% of the revised project cost.
Remaining budget: ₹1444 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.