Original Cost
₹1064 Cr
Baseline estimate
Revised Cost
₹1104 Cr
Latest approved cost
Expenditure
₹503 Cr
Spent to date
Utilization
45.6%
Of revised budget
Cost Status
+3.7%
+₹40 Cr increase
Remaining
₹601 Cr
Budget left
Spent
₹503 Cr
Remaining
₹601 Cr
Total
₹1104 Cr
Original Cost
₹1064 Cr
Revised Cost
₹1104 Cr
Increase
+₹40 Cr
Escalation
+3.7%
Project Approved
Construction / Implementation
Original End Date
19/09/2025
Revised Completion
31/10/2026
Completed
Cost has increased by ₹40 Cr (3.7%) from the original estimate of ₹1064 Cr.
Expenditure stands at ₹503 Cr, which is 45.6% of the revised project cost.
Remaining budget: ₹601 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.