4L PS from near Hunsur - KR Nagar Junction to near Yalachahalli village KR Nagara - Yelawala Road Junction fcrom Km 169.000 to Km 195.550 of NH-275 Pkg-IV
Original Cost
₹1063 Cr
Baseline estimate
Revised Cost
₹952 Cr
Latest approved cost
Expenditure
₹286 Cr
Spent to date
Utilization
30.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹666 Cr
Budget left
Budget Utilization
30.1%Spent
₹286 Cr
Remaining
₹666 Cr
Total
₹952 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/04/2027
Revised Completion
06/04/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1063 Cr — no cost escalation recorded.
Expenditure stands at ₹286 Cr, which is 30.1% of the revised project cost.
Remaining budget: ₹666 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L PS from near Hunsur - KR Nagar Junction to near Yalachahalli village KR Nagara - Yelawala Road Junction fcrom Km 169.000 to Km 195.550 of NH-275 Pkg-IV is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1063.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L PS from near Hunsur - KR Nagar Junction to near Yalachahalli village KR Nagar"?
- 4L PS from near Hunsur - KR Nagar Junction to near Yalachahalli village KR Nagara - Yelawala Road Junction fcrom Km 169.000 to Km 195.550 of NH-275 Pkg-IV is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1063 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1063 Cr and has been revised to ₹952 Cr — a cost overrun of -10.4%. Expenditure to date: ₹286 Cr (30.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L PS from near Hunsur - KR Nagar Junction to near Yalachaha is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618872. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L PS from near Hunsur - KR Nagar Junction to near Yalachaha is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.