Original Cost
₹525 Cr
Baseline estimate
Revised Cost
₹657 Cr
Latest approved cost
Expenditure
₹254 Cr
Spent to date
Utilization
38.7%
Of revised budget
Cost Status
+25.2%
+₹132 Cr increase
Remaining
₹403 Cr
Budget left
Spent
₹254 Cr
Remaining
₹403 Cr
Total
₹657 Cr
Original Cost
₹525 Cr
Revised Cost
₹657 Cr
Increase
+₹132 Cr
Escalation
+25.2%
Project Approved
Construction / Implementation
Original End Date
01/05/2025
Revised Completion
15/07/2026
Completed
Cost has increased by ₹132 Cr (25.2%) from the original estimate of ₹525 Cr.
Expenditure stands at ₹254 Cr, which is 38.7% of the revised project cost.
Remaining budget: ₹403 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.