Roads & HighwaysIPM · Central Project +26.5% overrun#618640

4L of Urga - Pathalgaon from Km. 70.200 to km. 157.745 of NH-130A

Ministry of Road Transport & HighwaysChhattisgarh
Revised Cost: ₹2860 CrUtilization: 39.2%Overrun: +₹599 Cr

Original Cost

₹2261 Cr

Baseline estimate

+27% overrun

Revised Cost

₹2860 Cr

Latest approved cost

Expenditure

₹1121 Cr

Spent to date

Utilization

39.2%

Of revised budget

Escalated

Cost Status

+26.5%

+₹599 Cr increase

Remaining

₹1739 Cr

Budget left

Budget Utilization

39.2%
0%25%50%75%100%

Spent

₹1121 Cr

Remaining

₹1739 Cr

Total

₹2860 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2261 Cr

Revised Cost

₹2860 Cr

Increase

+₹599 Cr

Escalation

+26.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/08/2026

Revised Completion

31/10/2026

Completed

Project Details

Project Code618640
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹2261 Cr
Revised Cost₹2860 Cr
Expenditure₹1121 Cr
Original End Date08/08/2026
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹599 Cr (26.5%) from the original estimate of ₹2261 Cr.

Expenditure stands at ₹1121 Cr, which is 39.2% of the revised project cost.

Remaining budget: ₹1739 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Urga - Pathalgaon from Km. 70.200 to km. 157.745 of NH-130A is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2261.00 Cr, later revised to ₹2860.36 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Urga - Pathalgaon from Km. 70.200 to km. 157.745 of NH-130A"?
4L of Urga - Pathalgaon from Km. 70.200 to km. 157.745 of NH-130A is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹2261 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2261 Cr and has been revised to ₹2860 Cr — a cost overrun of +26.5%. Expenditure to date: ₹1121 Cr (39.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Urga - Pathalgaon from Km. 70.200 to km. 157.745 of NH is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618640. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Urga - Pathalgaon from Km. 70.200 to km. 157.745 of NH is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.