Original Cost
₹2261 Cr
Baseline estimate
Revised Cost
₹2860 Cr
Latest approved cost
Expenditure
₹961 Cr
Spent to date
Utilization
33.6%
Of revised budget
Cost Status
+26.5%
+₹599 Cr increase
Remaining
₹1899 Cr
Budget left
Spent
₹961 Cr
Remaining
₹1899 Cr
Total
₹2860 Cr
Original Cost
₹2261 Cr
Revised Cost
₹2860 Cr
Increase
+₹599 Cr
Escalation
+26.5%
Project Approved
Construction / Implementation
Original End Date
08/08/2026
Revised Completion
08/08/2026
Completed
Cost has increased by ₹599 Cr (26.5%) from the original estimate of ₹2261 Cr.
Expenditure stands at ₹961 Cr, which is 33.6% of the revised project cost.
Remaining budget: ₹1899 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.