Km 230.385 to Km 281.391 of NH-227A
Original Cost
₹1431 Cr
Baseline estimate
Revised Cost
₹1927 Cr
Latest approved cost
Expenditure
₹191 Cr
Spent to date
Utilization
9.9%
Of revised cost
Cost Overrun
+34.7%
+₹496 Cr
Remaining
₹1736 Cr
Budget left
Spent
₹191 Cr
Remaining
₹1736 Cr
Total
₹1927 Cr
9.9%
Utilized
Original Cost
₹1431 Cr
Revised Cost
₹1927 Cr
Increase
+₹496 Cr
Escalation
+34.7%
Project Approved
Construction / Implementation
Original End Date
2026-11-19
Revised Completion
2028-11-19
Completed
Cost has increased by ₹496 Cr (34.7%) from the original estimate of ₹1431 Cr.
Expenditure stands at ₹191 Cr, which is 9.9% of the revised project cost.
Remaining budget: ₹1736 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.