Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /4L of Shakral Village to Dhalli Section from Km 14
Roads & HighwaysIPM · Central Project +47.3% Overrun#618922

4L of Shakral Village to Dhalli Section from Km 146.300 to Km 156.560 Shimla Bypass - Pkg II and Shimla connectivity from Km 0.000 to Km 0.725 of NH-5

Ministry of Road Transport & HighwaysHimachal PradeshData: 2026-05
Revised Cost: ₹2881 CrUtilization: 43.9%Overrun: +₹925 Cr

Original Cost

₹1956 Cr

Baseline estimate

+47%

Revised Cost

₹2881 Cr

Latest approved cost

Expenditure

₹1266 Cr

Spent to date

Utilization

43.9%

Of revised budget

Escalated

Cost Status

+47.3%

+₹925 Cr increase

Remaining

₹1615 Cr

Budget left

Budget Utilization

43.9%
0%25%50%75%100%

Spent

₹1266 Cr

Remaining

₹1615 Cr

Total

₹2881 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1956 Cr

Revised Cost

₹2881 Cr

Increase

+₹925 Cr

Escalation

+47.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/03/2027

Revised Completion

31/12/2027

Completed

Project Details

Project Code618922
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHimachal Pradesh
Data Month2026-05

Financial & Timeline

Original Cost₹1956 Cr
Revised Cost₹2881 Cr
Expenditure₹1266 Cr
Original End Date03/03/2027
Revised Date31/12/2027

Project Intelligence

Cost has increased by ₹925 Cr (47.3%) from the original estimate of ₹1956 Cr.

Expenditure stands at ₹1266 Cr, which is 43.9% of the revised project cost.

Remaining budget: ₹1615 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Frequently Asked Questions

What is IPM project "4L of Shakral Village to Dhalli Section from Km 146.300 to Km 156.560 Shimla Byp"?
4L of Shakral Village to Dhalli Section from Km 146.300 to Km 156.560 Shimla Bypass - Pkg II and Shimla connectivity from Km 0.000 to Km 0.725 of NH-5 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹1956 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost was ₹1956 Cr and has been revised to ₹2881 Cr — a cost overrun of +47.3%. Expenditure to date: ₹1266 Cr (43.9% of revised cost). Data as of 2026-05.
Which ministry is responsible for this project?
4L of Shakral Village to Dhalli Section from Km 146.300 to K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618922. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Shakral Village to Dhalli Section from Km 146.300 to K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview