Bridge including Manihari Bypass
Original Cost
₹1955 Cr
Baseline estimate
Revised Cost
₹1978 Cr
Latest approved cost
Expenditure
₹1821 Cr
Spent to date
Utilization
92.0%
Of revised cost
Cost Overrun
+1.2%
+₹23 Cr
Remaining
₹157 Cr
Budget left
Spent
₹1821 Cr
Remaining
₹157 Cr
Total
₹1978 Cr
92.0%
Utilized
Original Cost
₹1955 Cr
Revised Cost
₹1978 Cr
Increase
+₹23 Cr
Escalation
+1.2%
Project Approved
Construction / Implementation
Original End Date
2024-10-31
Revised Completion
2026-12-31
Completed
Cost has increased by ₹23 Cr (1.2%) from the original estimate of ₹1955 Cr.
Expenditure stands at ₹1821 Cr, which is 92.0% of the revised project cost.
Remaining budget: ₹157 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.